Reading Time: 6 minutes Updates for 05.05.2021 The construction works are progressing fast and for now the building is 50% ready. Now the team is proceeding with the following works: Masonry of inter-apartment walls, as well as masonry of interior partitions for the 2nd floor; Construction of 2.5th floor; […]